估算/费用估算:estimate/cost estimate;
估算类型:types of estimate;
详细估算:是偏差幅度最小的估算,defined estimate;
设备估算:equipment estimate;
分析估算:analysis estimate;
报价估算:proposal estimate;
控制估算:control estimate;
初期控制估算:interim control estimate/initial control estimate
批准的控制估算:initial approved cost
核定估算:check estimate
首次核定估算:first check estimate
二次核定估算:production check estimate
人工时估算:man hour estimate
材料费用/直接材料费用:material cost/direct material cost
设备费用/设备购买费用:equipment cost/purchased cost of equipment
散装材料费用/散装材料购买费用:bulk material cost/purchased cost of bulk material
施工费用:construction cost
施工人工费用:labor cost/construction force cost
设备安装人工费用:labor cost associated with equipment
散装材料施工安装人工费用:labor cost associated with bulk materials
人工时估算定额:standard manhours
施工人工时估算定额:standard labor manhours
标准工时定额:standard hours
劳动生产率:labor productivity/productivity factor/productivity ratio
修正的人工时估算值:adjusted manhours
人工时单价:manhours rate
施工监督费用:cost of construction supervision
施工间接费用:cost of contruction indirects
分包合同费用/现场施工分包合同费用:subcontract cost/field subcontract cost