发布于:2007-09-09 08:38:09
来自:注册考试/注册土木工程师
[复制转发]
常用造价英语词汇
估算/费用估算:estimate/cost estimate;
估算类型:types of estimate;
详细估算:是偏差幅度最小的估算,defined estimate;
设备估算:equipment estimate;
分析估算:analysis estimate;
报价估算:proposal estimate;
控制估算:control estimate;
初期控制估算:interim control estimate/initial control estimate
批准的控制估算:initial approved cost
核定估算:check estimate
首次核定估算:first check estimate
二次核定估算:production check estimate
人工时估算:man hour estimate
材料费用/直接材料费用:material cost/direct material cost
设备费用/设备购买费用:equipment cost/purchased cost of equipment
散装材料费用/散装材料购买费用:bulk material cost/purchased cost of bulk material
施工费用:construction cost
施工人工费用:labor cost/construction force cost
设备安装人工费用:labor cost associated with equipment
散装材料施工安装人工费用:labor cost associated with bulk materials
人工时估算定额:standard manhours
施工人工时估算定额:standard labor manhours
标准工时定额:standard hours
劳动生产率:labor productivity/productivity factor/productivity ratio
修正的人工时估算值:adjusted manhours
人工时单价:manhours rate
施工监督费用:cost of construction supervision
施工间接费用:cost of contruction indirects
分包合同费用/现场施工分包合同费用:subcontract cost/field subcontract cost
公司本部费用:home office cost
公司管理费用:overhead
非工资费用:non payroll
开车服务费用:cost of start-up services
其他费用:other cost
利润/预期利润:profit/expected profit
服务酬金:service gains
风险:risk
风险分析:risk analysis
风险备忘录:risk memorandum
未可预见费:contingency
基本未可预见费:average contingency
最大风险未可预见费:maximum risk contingency
用户变更/合同变更:cilent change/contract change
认可的用户变更:approved client change
待定的用户变更:pending client change
项目变更:project change
内部变更:internalchange
批准的变更:authoried change
强制性变更:mandatory change
选择性变更:optional change
内部费用转换:internal transfer
认可的预计费用:anticipated approved cost
涨价值:escalation
项目费用汇总报告:project cost summary report
项目实施费用状态报告:project operation cost status report
总价合同:lump sum contract
偿付合同:reimbursible contract
预算:budget
全部回复(2 )
只看楼主 我来说两句抢地板回复 举报
回复 举报