安吉吉庆桥施工组织设计本工程系安吉县灵峰北路延伸段新建吉庆大桥工程。桥梁位于原吉庆桥东侧,桥梁中心里程为K0+598.351。该桥为左斜30°斜桥,桥梁全长198.28m,桥面纵坡为双向1.6%,变坡点位于该桥中心,竖曲线半径R=6500m。工程范围下部结构为钻孔灌注桩基础;承台、墩台身、盖梁;台帽;上部结构为20m+6×25m+20m后张法预应力空心板,简支结构,非伸缩缝墩顶采用桥面连续;桥面系及其附属工程。预期工期为265天(日历天),质量目标为优良。
回帖成功
经验值 +10
全部回复(1 )
只看楼主 我来说两句 抢板凳污水提升泵站压密注浆施工方案
Execution Plan for Compaction and Grouting
一、 前言Preface
污水提升泵站压密注浆主要针对其基坑底板下部的约1.8m厚的粉土,因其底板呈阶梯部,部份土体滑动,造成部份底板与其下部粉土的分离,而形成空洞,目前通过现场勘察,因破坏处为16×3×1.8m。因而要求采用注浆方式进行土体加固。This plan is mainly aimed at about 1.8m THK powder soil in the bottom slab of foundation pit. As the bottom slab is in a step and part of the soil is slided, some slabs are separated from the powder soil. So the hollows turn up. After the site investigation, as the broken area is 16*3*1.8m, method of grouting should be adopted for the soil strengthening.